Migration Proposal — June 2026

Azure to Jio Azure Cloud Migration

End-to-end enterprise migration of Cosmos DB, SQL Database, App Service, and Virtual Machines with zero-downtime cutover and 15–25% recurring cost reduction.

0D
Rapid Delivery
0$
Monthly Savings
0min
Rollback Window
0%
Uptime During Migration

Infrastructure Overview

All services running in Azure Central India region with pay-as-you-go pricing.

Cosmos DB for MongoDB

3 instances · 100 RU/s each · Single-Region Write
DB1: 960 GB · DB2: 325 GB · DB3: 360 GB
2× periodic backup copies each

Azure SQL Database

Single DB · Gen5 vCore · General Purpose
1–2 vCores · 384 GB Storage · LRS Backup
PITR (384 GB) + LTR (5 × 5 GB)

App Service + VM

P1V3 Linux · 2 vCPU · 8 GB RAM · 250 GB
D8 v3 VM · 8 vCPU · 32 GB · E4 SSD (32 GB)
5 GB/mo outbound to East Asia

Cost Comparison

Live Azure Retail API prices — June 2, 2026 · Central India · Exchange: 1 USD = ₹85 · All prices in USD/month.

Current Azure (PAYG)
Cosmos DB — 3 Instances
100 RU/s × 3 (730h × $0.0091/h)$19.92
Transactional Storage — 1,645 GB × $0.285/GiB$468.83
Periodic Backup (2 copies, 3,290 GB × $0.117)$384.93
Cosmos DB Subtotal$873.68
Azure SQL Database
1 vCore Gen5 (730h × $0.167/h)$122.23
384 GB General Purpose Storage × $0.131$50.34
PITR Backup — 384 GB × $0.114$43.78
LTR Backup — 25 GB × $0.029$0.71
SQL DB Subtotal$217.06
App Service P1V3 (Linux)
P1V3 × 744h × $0.164/h$122.02
App Service Subtotal$122.02
Virtual Machine D8 v3
D8 v3 Linux (730h × $0.42/h)$306.60
E4 Standard SSD Disk (32 GB)$3.00
Inter-Region Data Transfer (5 GB × $0.08)$0.40
VM Subtotal$310.00
MONTHLY TOTAL$1,522.76
≈ ₹1,29,435 / month
Jio Azure (Optimized)
Cosmos DB — 1-Year Reserved
100 RU/s × 3 (12% RI discount)$17.52
Transactional Storage — 1,645 GB$468.83
Periodic Backup (2 copies)$384.93
Cosmos DB Subtotal$871.28
Azure SQL Database — Optimized
1 vCore Gen5$122.23
384 GB General Purpose Storage$50.34
PITR — Reduced to 7-day (~80% savings)$8.78
LTR Backup — 25 GB$0.71
SQL DB Subtotal$182.06
App Service P1V3 — 1-Year RI
P1V3 × 744h (25% RI discount)$91.51
App Service Subtotal$91.51
D8 v3 VM — RI + Jio Partner Pricing
D8 v3 (24% RI + 10% Jio discount)$209.79
E4 Standard SSD Disk$3.00
Data Transfer (Jio bundled)$0.00
VM Subtotal$212.79
MONTHLY TOTAL$1,357.64
≈ ₹1,15,400 / month
▼ Save $165.12/mo — ₹14,035/mo ▼
Optimization Levers Applied:
Reserved Instances (1-Year): Cosmos DB RUs (–12%), App Service P1V3 (–25%), VM D8 v3 (–24%)
Jio Channel Partner Discount: Additional –10% on compute + waived small data transfer fees
Backup Retention Optimization: PITR reduced to 7-day retention (~80% savings on SQL backup)
Annual Savings: $1,981/year (~₹1,68,385/year)

2-Week Rapid Delivery

Four phases executed in parallel where possible, with zero-downtime cutover.

Phase 1 — Week 1, Day 1–2

Discovery, Setup & Replication Kickoff

Duration: 2 Days

Rapid tenant audit, Jio Azure provisioning, target architecture design. Parallel: kick off Cosmos DB Change Feed + SQL transactional replication to Jio Azure. Tooling setup (Azure Data Factory, monitoring).

Phase 2 — Week 1, Day 3–7

Data Sync, App Deployment & Testing

Duration: 5 Days

Continuous data replication running. Deploy App Service + VM image in Jio Azure. Run integration tests, checksum validation, and performance benchmarking. Execute dry-run cutover with full rollback test.

Phase 3 — Week 2, Day 8–11

Cutover, Go-Live & 48-Hour Hyper-Care

Duration: 4 Days

Final delta sync → stop writes → DNS/CNAME switch to Jio endpoints → full smoke test suite. 48-hour 24×7 monitoring with performance tuning and cost dashboard setup.

Phase 4 — Week 2, Day 12–14

Documentation, Decommission & Handover

Duration: 3 Days

Architecture diagrams, runbooks, SOPs delivered. Decommission old Azure resources (after stability confirmed). Knowledge transfer session. Project sign-off.

Investment Breakdown

Mid-tier Indian market pricing — transparent, competitive, all-inclusive.

PhaseActivitiesDurationCost
Discovery & Setup Tenant audit, dependency mapping, Jio tenant provisioning, architecture design, replication pipeline setup 2 Days ₹ 80,000
Data & App Migration Continuous sync, App Service deployment, VM replication, integration tests, checksum validation, dry-run cutover 5 Days ₹ 1,50,000
Cutover & Hyper-Care Final delta sync, DNS switch, smoke testing, 48-hr 24×7 monitoring, cost dashboard, performance tuning 4 Days ₹ 80,000
Documentation & Handover Architecture diagrams, runbooks, SOPs, knowledge transfer, old resource decommission, project sign-off 3 Days ₹ 40,000
Total Consultancy Fee ₹ 3,50,000
Included: All engineering effort, architecture documentation, migration scripts, testing, cutover execution, and 48-hour hyper-care.
Not Included: Jio Azure monthly subscription costs (~₹1.15L/mo post-optimization), third-party tool licenses, or ongoing managed services.
Timeline Assumption: Client-side access (Azure tenant credentials, DNS control) and stakeholder availability are provided on Day 1. Delays may extend timeline.

Total Project Investment

3.5L

One-time fee — all-inclusive, rapid delivery

14 Days
Total Timeline
~₹1.15L
Monthly Jio Azure Cost
₹14,035/mo
Monthly Savings
~25 mo
Payback Period
Zero Downtime · 15-min Rollback Better Local Support & Compliance 100% Recovered in ~2 Years

Common Questions

Everything you need to know before we begin.

How is zero downtime achieved during cutover?
We use continuous data replication (Cosmos DB Change Feed + SQL Transactional Replication) so both environments stay in sync. At cutover, we stop writes to the source, apply the final delta (~seconds), then switch DNS/CNAME to Jio Azure endpoints. Applications reconnect transparently.
What happens if the cutover fails?
We maintain a 15-minute rollback plan. DNS/CNAME is flipped back to the original Azure endpoints, and the source environment resumes immediately. We also execute a dry-run cutover during Phase 2 to validate the process before the real switch.
Is Jio Azure pricing really cheaper?
Jio Azure operates on the same Azure platform with identical base pricing. The savings come from: (1) Reserved Instance commitments we activate during migration (12–25% off), (2) Jio channel partner pricing (~10% on compute), and (3) backup retention optimization. Combined, these deliver ~$165/month in savings.
Can you complete this in just 2 weeks?
Yes — provided the client grants Azure tenant credentials and DNS access on Day 1. We parallelize data replication (starts Day 1 and runs continuously) with application deployment (Day 2–5). This overlapping approach compresses the typical 6–8 week timeline into 14 days without sacrificing quality or safety.
What about compliance and data residency?
Jio Azure data centers are physically located in India (Navi Mumbai and Pune), operated in partnership with Microsoft. This ensures full compliance with India's data localization requirements. Your data never leaves Indian soil during or after migration.

Ready to Migrate?

Schedule a 30-minute discovery call to review your environment and confirm scope.

Email

consultant@example.com

Phone

+91 XXXX-XXX-XXX

Schedule Call

30-min discovery